Issues of fairness in bids and saving ratepayer dollars surround this 20-acre mountain of compacted refuse know as Sudbury Landfill Area Six. The controversy centers over whether city officials should accept the lowest bid for an Area Six closure project and save $100,000, or consider that lowest bid as insufficient and go with the next lowest bidder to maintain fairness. City Council will review the bids at its next meeting on Wednesday evening at City Hall.

Stories this photo appears in:

Walla Walla City Council to sift through contract to close landfill

A relatively new process will replace the need for a liner by utilizing the natural process of evapotranspiration.

WALLA WALLA — On Wednesday, City Council members will again discuss whether they should award a $1.5 million contract to Boss Construction Inc. or consider that company's bid as insufficient and pay $100,000 more for the next highest bidder.But even at $1